Colliers Wood
42 Station Road is Clarion Housing Group’s 100% affordable development in Colliers Wood. It’s being delivered in partnership with The Hill Group and Merton Council. It provides 98 energy-efficient one-, two- and three-bedroom homes, all for social rent and all for local people. The homes are in two blocks: Block A has nine storeys over ground-floor commercial units, and Block B rises to twelve storeys. Twelve of the homes are designed to wheelchair-accessible M4(3) standard. The scheme also plays a key part in Clarion’s wider regeneration work in Merton.
Home > Residential > Colliers Wood, 100% social rent apartments
Client: Clarion Housing Group
Main Contractor: Hill Partnerships (The Hill Group)
Location: 42 Station Road, Colliers Wood, Merton, London SW19 2LP
Sector: Residential
About the Project
42 Station Road is Clarion Housing Group’s 100% affordable development in Colliers Wood. It’s being delivered in partnership with The Hill Group and Merton Council. It provides 98 energy-efficient one-, two- and three-bedroom homes, all for social rent and all for local people. The homes are in two blocks: Block A has nine storeys over ground-floor commercial units, and Block B rises to twelve storeys. Twelve of the homes are designed to wheelchair-accessible M4(3) standard. The scheme also plays a key part in Clarion’s wider regeneration work in Merton.
Our Role
GA Interiors was appointed by Hill Partnerships across three packages on the scheme. We delivered the SFS external framing, then the full internal drylining package, and then a separate passive fire-stopping package. Our teams were on site from the frame stage in late 2024 right through to final making good and snagging.
Scope of Works
- SFS framing: Hadley SFS infill walls across both blocks, floor by floor, built ahead of the external envelope.
- Partitions and party walls: metal stud party walls, internal partitions and storage cupboards to all 98 apartments, plus shaft walls to risers, smoke shafts and AOVs.
- Communal areas: dot and dab linings to corridors and staircases, cross-corridor and riser walls, and reveals to lifts, fire doors and entrance doors.
- Ceilings: MF suspended ceilings in apartments, corridors and staircases, grid ceilings to HIU cupboards, and 300×300 access panels throughout the corridors.
- Soffit insulation: soffit insulation and boarding to the exposed top-floor apartments.
- Finishes: Thistle Multi-Finish plastering, full tape and jointing, post box openings formed at first fix, then final making good and snagging.
- Passive fire protection: fire stopping to service penetrations, communal areas and risers using Nullifire, Promat and intumescent sealant systems. All of it was recorded on OneTrace, delivered by our FIRAS-approved team.
Challenges & How We Delivered
This tight town-centre site sits next to homes and a school route:
- There was no on-site parking. Deliveries were limited to rigid vehicles, booked in advance and kept out of the school-run hours.
- Every delivery was offloaded by Moffett or forklift, then lifted by tower crane to the hoist or straight to the floor. That meant windy days could stop loading entirely.
- No work could start before 8am because of the neighbours. Strict dust control was in place: no sweeping, with extraction vacuums and dust-extraction tools used throughout.
- We worked alongside M&E and other trades on live floors, often out of sequence and across two blocks at once.
We delivered by working floor by floor and block by block. SFS went in ahead of the envelope, and party walls and partitions followed, keeping pace with the frame. Ceilings closed out as services were signed off. We worked closely with Hill’s site team on the details that needed design input, including riser boxing, letterbox risers and fire door details. We also planned material deliveries around the crane and hoist. Once the hoist was taken down, we went back to close out the hoist openings and finish those apartments. Weekly progress reports, Hill’s digital quality inspections and OneTrace records gave Hill full visibility from start to finish.
The Result
98 high-quality homes for social rent, finished to a consistent standard across two blocks. They will give local families in Merton secure, energy-efficient places to live. Taking on SFS, drylining and fire stopping meant Hill had one team accountable from frame to finish.